10 Dec Synthesize information from all previous assignments into a PowerPoint presentation that showcases the project successes to the key customer(s) and/or stakeholder(s).? Your presentation shoul
Overview
Congratulations! You’re ready to present a summary of all your hard work to your customer(s) and stakeholder(s)!
Instructions
For this assignment, complete the following:
Synthesize information from all previous assignments into a PowerPoint presentation that showcases the project successes to the key customer(s) and/or stakeholder(s).
Your presentation should have at least 10 slides:
A title slide
At least 8 informational slides
A final slide for sources
Do not include content from previous assignments word-for-word. Instead, incorporate instructor feedback you received on previous activities and assignments, and then summarize the key information for your presentation.
When creating your presentation, emphasis should be placed on addressing your audience with an appropriate tone. Your slides should not be bullet-pointed lists, but a professional summary of the successes of your project for the stakeholders.
Include detailed speaker notes that expand on the information presented in the slides.
All slides should include at least 50 words of speaker notes, except for the title and sources slides.
Speaker notes are used to guide what you would say if you were presenting to your customer(s). You can use speaker notes to remind yourself of details to discuss that aren’t listed on the slide. These notes could include details on project budget, troubleshooting and eliminating roadblocks, timeline adjustments, etc.
Instructions
| Week 6 Assignment – Project Tasks and Timeline Instructions: Carefully look through the "Sample" tab. Pay close attention to the amount of detail included, and the formatting and organization of the list. You will use this sample list as a guide to create your own list of tasks, but you should not duplicate the content from the sample exactly. Navigate to the third tab titled, "Blank Template – Fill This In" and complete the following: 1. In the “Activity” column, outline a plausible list of tasks needed to complete your chosen project. You may group tasks together as in the Sample tab, or list each task separately. 2. In the “Start Date”, “End Date”, and “Days to Complete” columns, estimate plausible timelines for each task or group of tasks. In the first row, highlighted in yellow, give a start and end date for the project as a whole. tc={E7F4959B-F80D-4A4D-B776-698FBD452113}: [Threaded comment] Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924 Comment: Recommend adding language to clearly point out that the three tabs are at the bottom and that they are not to duplicate the content from the sample. |
Sample
| Project Tasks and Timeline Developed by John Smith October 2022 | |||
| Activity | Days to Complete | Start Date | End Date |
| Construction Plan | 253 | Saturday, January 1, 2022 | Sunday, September 11, 2022 |
| Planning Activites | 30 | Saturday, January 1, 2022 | Monday, January 31, 2022 |
| Finalize Plans | |||
| Sign Contract to Proceed | |||
| Construction Activities | 45 | Monday, January 31, 2022 | Thursday, March 17, 2022 |
| Prepare Site | |||
| Prepare Foundation for Property | |||
| Establish Framing for Property | |||
| Exterior Work Activities | 30 | Thursday, March 17, 2022 | Saturday, April 16, 2022 |
| Install Roof | |||
| Install Windows | |||
| Install Doors | |||
| Install Bricks | |||
| Install Siding | |||
| Interior Work Activities | 120 | Saturday, April 16, 2022 | Sunday, August 14, 2022 |
| Install Insulation | |||
| Install Drywall | |||
| Install Plumbing & Related Fixtures | |||
| Install Electrical & Related Fixtures | |||
| Install HVAC | |||
| Install Cabinets | |||
| Install Flooring | |||
| Install Appliances | |||
| Grounds Work Activities | 14 | Sunday, August 14, 2022 | Sunday, August 28, 2022 |
| Install Driveway | |||
| Install Sidewalks | |||
| Install Fencing | |||
| Install Deck | |||
| Lay Sod & Plants | |||
| Final Acceptance | 14 | Sunday, August 28, 2022 | Sunday, September 11, 2022 |
| Clean Up Property for Inspection (Cleaning Service) | |||
| Inspection by Local Government | |||
| Address Issues from Government Inspection | |||
| Inspection by Owner | |||
| Address Issues from Owner Inspection | |||
| Turn Property Over to Owner |
Blank Sheet
| Construction Progress Report Name: Tyrell Wilson Date: 11/28/2022 | |||
| Activity | Days to Complete | Start Date | End Date |
| Construction Plan | 253 | Tuesday, February 1, 2022 | Wednesday, October 12, 2022 |
| Planning Activites | 30 | Tuesday, February 1, 2022 | Wednesday, March 2, 2022 |
| Finalize Plans | 28 | Tuesday, February 1, 2022 | Monday, February 28, 2022 |
| Sign Contract to Proceed | 2 | Monday, Feburary 28, 2022 | Wednesday, March 2, 2022 |
| Construction Activities | 45 | Wednesday, March 2, 2022 | Saturday, April 16, 2022 |
| Prepare Site | 7 | Wednesday, March 2, 2022 | Wednesday, March 9, 2022 |
| Prepare Foundation for Property | 13 | Wednesday, March 9, 2022 | Tuesday, March 22, 2022 |
| Establish Framing for Property | 25 | Tuesday, March 22, 2022 | Saturday, April 16, 2022 |
| Exterior Work Activities | 30 | Saturday, April 16, 2022 | Monday, May 16, 2022 |
| Install Roof | 7 | Saturday, April 16, 2022 | Saturday, April 23, 2022 |
| Install Windows | 1 | Saturday, April 23, 2022 | Sunday, April 24, 2022 |
| Install Doors | 1 | Monday, April 25, 2022 | Tuesday, April 26, 2022 |
| Install Bricks | 6 | Tuesday, April 26, 2022 | Monday, May 2, 2022 |
| Install Siding | 14 | Monday, May 2, 2022 | Monday, May 16, 2022 |
| Interior Work Activities | 120 | Monday, May 16, 2022 | Tuesday, September 13, 2022 |
| Install Insulation | 15 | Monday, May 16, 2022 | Tuesday, May 31, 2022 |
| Install Drywall | 15 | Tuesday, May 31, 2022 | Thursday, June 14, 2022 |
| Install Plumbing & Related Fixtures | 15 | Thursday, June 14, 2022 | Wednesday, June 29, 2022 |
| Install Electrical & Related Fixtures | 15 | Wednesday, June 29, 2022 | Thursday, July 14, 2022 |
| Install HVAC | 15 | Thursday, July 14, 2022 | Friday, July 29, 2022 |
| Install Cabinets | 15 | Friday, July 29, 2022 | Saturday, August 13, 2022 |
| Install Flooring | 15 | Saturday, August 13, 2022 | Sunday, August 28, 2022 |
| Install Appliances | 15 | Sunday, August 28, 2022 | Monday, September 12, 2022 |
| Grounds Work Activities | 15 | Monday, September 12, 2022 | Tuesday, September 27, 2022 |
| Install Driveway | 3 | Monday, September 12, 2022 | Monday, September 15, 2022 |
| Install Sidewalks | 3 | Monday, September 15, 2022 | Sunday, September 18, 2022 |
| Install Fencing | 3 | Sunday, September 18, 2022 | Wednesday, September 21, 2022 |
| Install Deck | 3 | Wednesday, September 21, 2022 | Saturday, September 24, 2022 |
| Lay Sod & Plants | 3 | Saturday, September 24, 2022 | Tuesday, September 27, 2022 |
| Final Acceptance | 14 | Tuesday, September 27, 2022 | Wednesday, October 12, 2022 |
| Clean Up Property for Inspection (Cleaning Service) | 4 | Wednesday, September 28, 2022 | Sunday, October 2, 2022 |
| Inspection by Local Government | 2 | Sunday, October 2, 2022 | Tuesday, October 4, 2022 |
| Address Issues from Government Inspection | 2 | Tuesday, October 4, 2022 | Thursday, October 6, 2022 |
| Inspection by Owner | 2 | Thursday, October 6, 2022 | Saturday, October 8, 2022 |
| Address Issues from Owner Inspection | 2 | Saturday, October 8, 2022 | Monday, October 10, 2022 |
| Turn Property Over to Owner | 2 | Monday, October 10, 2022 | Wednesday, October 12, 2022 |
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.