Chat with us, powered by LiveChat Which of the following items best describes a project Work Breakdown Structure (WBS)? - Essayabode

Which of the following items best describes a project Work Breakdown Structure (WBS)?

Which of the following items best describes a project Work Breakdown Structure (WBS)?

 

 a. a schedule depicting when project work will be performed   

 

b. a tool that the team uses to progressively divide deliverables into smaller and smaller pieces

 

c. a list of activities to complete the project work packages         

 

d. an organizational chart depicting who will perform project work

 

Which of the information below would NOT typically be included in the WBS dictionary for a specific work package?

 

 a. description of the work          

 

b. communication requirements              

 

c. activities         

 

d. expected duration

 

If a problem occurs during project execution, the WBS is helpful in understanding exactly where and why the problem occurred.

 

  a. True

 

  b. False

 

Which of the following statements concerning work packages is NOT correct?

 

 a. Work packages are activity elements with detailed descriptions of tasks and dependencies   

 

b. Work packages are the basis for subsequent project planning activities.          

 

c. Work packages are the basis for subsequent project control activities.              

 

d. Work packages are the elements at the lowest level of the WBS.

 

The work component at the lowest level of the WBS for which cost and duration can be estimated and managed is called the ______:

 

 a. work element             

 

b. activity            

 

c. work package               

 

d. control account

 

A WBS dictionary is a document that defines each of the terms used in the project scope statement.

 

  a. True

 

  b. False

 

A _________ is a written request or formal proposal to propose changes to any project planning component such as a document, project deliverable, or baseline (scope, cost, and time).

 

a. scope statement        

 

b. project charter            

 

c. change request           

 

d. request for proposal (RFP)

 

Plan scope management is the process of creating a project scope statement.

 

  a. True

 

  b. False

 

When a project team needs to construct a WBS, it needs to include in its planning team a subject matter expert (SME) who understands how each segment of the work will be accomplished.

 

  a. True

 

  b. False

 

The priority of the product in agile is more significant than in traditional project management, as the outcome, or product, will drive the elaboration of the project.

 

  a. True

 

  b. False

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?